Waterfront manager Katherine Dugmore has now updated city councillors on the waterfront development. She says the project at Prince Arthur's Landing has run 5 million dollars over budget. 2.2 million of that will have to be taken from phase two of the project. Dugmore says it's too early to say what buget cuts will be necessary to make up for that 2.2 million dollar shortfall for phase two.